Rénovation of “La Maladière”, old agricultural cooperative into a festive room

MontmelianImplementation concept submitted by: ASDER

Place: Montmelian, Metropole-Savoie, Savoie, Rhone-Alpes, France

Category (new/renovation): renovation with use change

Type of building
Kind of public use: building currently abandoned. Project: festive or exibition room + 1 appartment
Total effective area: 840 m²
Number of levels above earth: 3
Type of heating system: electrical (currrently not heated). On reflection.
Type of water heating system:  Warm water renewable (solar, wood energy) on reflection
Type of ventilation system: no ventilation system

Owner and Costs
Name of owner: Municipality of Montmelian
Date of renovation: planned for 2014/2015
Total cost: 4 M € in several blocks
Financing resources: municipality + subsidies

Short description of the pilot project
Creation of 2 festive rooms + 1 keeper housing in the former premises of a cooperative room.  Current phase of the development: program

Process and planning quality
Development of the program late 2013
Construction: building permit 2014
Works: 2 semester 2014

Implementation of service package
The MountEE support on this project is defined as follows:
– Environmental program proposal integrated into the program
– Opportunity Analysis for the heating system of the building and its surroundings
– Follow responses from project management to take into account environmental objectives.
– Identification of control points of the environmental program at different phases of the project

Energy and Utilities

a)    Primar energy demand
Reduction needs with low consumation renovation goals on building

 b)    Renewable energy
Solar, wood energy

Health and Comfort
Strong internal gains associated with festive activity: targets large air renewal to improve thermal comfort and reduce the risk of nuisance to the neighborhood.

Building materials and constructions
Specific requirements at this level will be included in the tender documents: max emission rate products, environmental labels and finishing products

Special methods
Use of ENERBUILD Referential

Lessions learned
Setting up a help desk at the beginning of the project / Help for setting goals and monitoring their outfits throughout the project

Rénovation of “La Maladière”, old agricultural cooperative into a festive room

MontmelianImplementation concept submitted by: ASDER

Place: Montmelian, Metropole-Savoie, Savoie, Rhone-Alpes, France

Category (new/renovation): renovation with use change

Type of building
Kind of public use: building currently abandoned. Project: festive or exibition room + 1 appartment
Total effective area: 840 m²
Number of levels above earth: 3
Type of heating system: electrical (currrently not heated). On reflection.
Type of water heating system: Warm water renewable (solar, wood energy) on reflection
Type of ventilation system: no ventilation system

Owner and Costs
Name of owner: Municipality of Montmelian
Date of renovation: planned for 2014/2015
Total cost: 4 M € in several blocks
Financing resources: municipality + subsidies

Short description of the pilot project
Creation of 2 festive rooms + 1 keeper housing in the former premises of a cooperative room. Current phase of the development: program

Process and planning quality
Development of the program late 2013
Construction: building permit 2014
Works: 2 semester 2014

Implementation of service package
The Mountee support on this project is defined as follows:
– Environmental program proposal integrated into the program
– Opportunity Analysis for the heating system of the building and its surroundings
– Follow responses from project management to take into account environmental objectives.
– Identification of control points of the environmental program at different phases of the project

Energy and Utilities

a) Primar energy demand
Reduction needs with low consumation